The Uma Oya Project
The Uma Oya Project
Selected
transcripts about the Uma Oya Project from a letter addressed to the
Hon.President by me on the 2nd Feb. 2015.
This
letter was acknowledged by the Assistant Secretary to the President on 16th
March, 2015 and forwarded by him to the Secretary, Ministry of Mahaweli
Development and Environment for necessary action in accordance with the
existing rules and regulations.
Transcripts
Subject : 'Uma Oya' tunnel leak at Karandagolla.
1.
'Yesterday's (1st
Feb, 2015) revelation by Sirasa of the gigantic water leak within the tunnel at
Karandagolla, makes it, I believe, for the government and the executive
president to take a quick decision without any delay. The reasons for this are
under mentioned.
2.
'When the tunnel,
from the Kotmale dam to the powerhouse at Atabage, was being constructed, at
some point within the tunnel, an unexpected crack opened and water gushed out.'
3.
'Regarding the
Kotmale project, it was assumed that the quality of the rock, through which the
tunnel was to be excavated, was suitable, so that there was no need for
concrete lining the tunnel, which was an economic advantage. However, the then professor
of Geology of the Peradeniya University, Prof Vithanage, expressed concerns on
this, saying that the 'granite' was suspect. But, his views were disregarded
and the project continued under the Accelerated Mahaweli. But Prof.Vitahanage
was correct. As the Swedish Contractors 'Skauska Cementjutriet', were reliable
and experienced in this field, they probably expected this to occur at some
stage and were prepared at the very moment a large leak appeared and in a very
short time, were able to rectify the situation, Thereafter, the contractors
concreted the tunnel sections where the granite was suspect.'
4.
'The same thing is
now happening at Karandagolla, except that the Iranians don't have an inkling
of what is happening.'
5.
'A vast system of
interconnected caverns and reservoirs lie within the rock formations of the
hilly regions of our island. Water accumulates in these caverns. It is this
water which is tapped up from the wells and oozes from the springs at the
'foot' of hills and mountains and feed the perennial streams and the major
rivers of Sri Lanka. The empty deep wells indicate that the water in these
reservoirs are depleted and has occurred progressively since the 25th December
2014, when the gush opened in the tunnel at Karandagolla.
6.
'The Iranians and
their Sri Lankan counterparts of the Uma Oya project are totally ignorant of
these matters.'
7.
'They do not
understand the serious implications of the gigantic water leak which is
happening at present and they are dabbling about with the tremendously
important natural underground reservoirs of water which are spread throught the
whole of the hill country of the island.'
8.
As water does not
seen to end in this gush, the worst fears that water from far reaching
underground caverns and reservoirs, beneath, Keppitipola, Nuwara Eliya,
Namunukula, Diyatalawa, Poonagala etc are also finding their wayout from
Karandagolla. I think the Iranians are playing for time till the gush ceases
and seal it but by that time, but the match would then be over and
desertification would have started, the tea industry would have collapsed and a
whole population would have had to suffer from this artificially induced
'drought', which would be irretrievable.
9.
'The only possible
thing to do is to concrete the openings of the tunnel and get the water to 'head
back' and 'head up' and stop the further loss of water from the underground
reservoirs of the hill country.'
10. 'Finally sir, I think it is not worth relying on the
Iranian management to solve the problem and risk the nation.'
Yasantha
De Silva
B.Sc (Agriculture)
Comments
Post a Comment